LOOK: Have a peek at the restoration plans for two Euclid Creek Tunnel shaft sites
- Posted by Jared Shepherd
- 4448 Views
- September 25th, 2015
- in Miscellaneous
- No Comments
Euclid Creek Tunnel shaft site 5 |
Euclid Creek Tunnel shaft site4 |
With the Euclid Creek Tunnel now complete on time and under budget, the Sewer District has set its sights on site restoration at two important community locations: Shaft 4 at Triangle Park at East 174 Street, and Shaft 5 at Nottingham Road and St. Clair Avenue.
The restoration contract was awarded to Nerone & Sons, Inc. on July 16, 2015. Substantial completion for the two site restorations shown above is expected in the spring of 2016.
The Euclid Creek Tunnel is the first of seven tunnels that will be completed under Project Clean Lake. When the Tunnel Dewatering Pump Station is complete at the end of 2016, the Euclid Creek Tunnel will be fully operational and will reduce combined sewer overflow by approximately 368 million gallons per year.